Commissioning Checklist Generator

Also known as System Test and Commissioning Checklist Generator

Generate a commissioning checklist with the test, method, acceptance criterion and reference written for every item.

Free ● Live 15 standards

Free to use. Sign up free to save, download and print.

Loading the Commissioning Checklist Generator…

What it produces

Commissioning checklist template

A commissioning checklist, or site acceptance test checklist, lists the tests that prove a system is installed, configured and working before it is handed over. Choose the systems on the site, from microwave links and two-way radio sites to fibre, IP networks, power plant, CCTV and Wi-Fi, and the tool writes each item's test, method, acceptance criterion and reference, grouped into sections and numbered by system and section.

The result and status cells start blank for the readings taken on site, and the acceptance criteria are typical commissioning norms to confirm against the project specification.

Standards

  • ITU-R P.530 and ITU-T G.826 and G.828 for microwave link performance
  • RFC 2544 and ITU-T Y.1564 for Ethernet throughput testing
  • ETSI EN 300 392 (TETRA), ETSI TS 102 361 (DMR) and TIA-102 (P25)
  • ISO/IEC 11801, ANSI/TIA-568 and IEC 61280-4-2 for structured cabling and fibre
  • AS/NZS 3000 and AS/NZS 1768 for electrical installation and lightning protection
  • ARPANSA RPS S-1 and ICNIRP for RF exposure

Sample

Sample: site acceptance test checklist for an RF site

The RF site infrastructure checklist for a tower or shelter, as the tool generates it: six of its 16 items, before any results are recorded.

Test IDSectionTest / CheckAcceptance CriteriaReference
SITE-MECH02Mechanical & InstallationCable management & entryFeeders supported per spec; entries sealed; both ends labelled.Manufacturer installation manual
SITE-PWR01Power & EnvironmentalMains supply & distributionCorrect voltage/phase; breakers rated and labelled; RCD tested and operational.AS/NZS 3000
SITE-ERTH03Earthing & BondingLightning & surge protectionLightning protection continuous; surge arrestors fitted and bonded.AS/NZS 1768; IEC 61643
SITE-RF02RF & Antenna SystemDistance-to-fault (DTF)No connector or cable fault; clean DTF signature end to end.Manufacturer
SITE-RF04RF & Antenna SystemRF exposure & signageExposure within limits; signage and barriers per the assessment.ARPANSA RPS S-1; ICNIRP
SITE-ACC02Acceptance & HandoverDefects cleared & sign-offNo open Category-1 defects; client acceptance signed.Project ITP

Each test ID is the system code, the section code and a number. Items with a numeric limit, such as the earth electrode resistance, set Pass or Fail from the reading typed on site.

FAQ

Frequently asked questions

Not here? Ask us

What goes into a commissioning checklist?

For each item: the test, how it is done, the acceptance criterion it must meet and the reference it comes from, then the reading and status recorded on site. Columns for who tested and witnessed it, the date and the evidence can be shown for an auditable record. Items are grouped into sections running from documentation and installation through power, earthing and bonding, RF, configuration, performance and integration to acceptance and handover.

Can I use it as a site acceptance test checklist?

Yes. A project is one site's acceptance pack: add every system on the site, such as a backhaul link, a base station and the RF site they share, and each row carries the system it belongs to. The acceptance test sheet groups the results by system and section, lists the test equipment used and ends with a sign-off block.

Can I rely on the acceptance criteria?

They are typical industry commissioning norms and a sensible starting point, but they are not a substitute for the project specification. Every criterion can be edited, so confirm each one against the contract. Result cells always start blank, and the tool never fills in a reading.

How are failures handled?

Marking an item as failed or defective raises it on a defect register, where you record the severity, owner and target date. Where an item has a numeric limit, the status can be set from the reading. The punch list exports separately for the retest.

What can I export, and where is my work stored?

You can copy the checklist to the clipboard, and when you are signed in you can export it to CSV or an Excel workbook, export the outstanding items or the punch list to CSV, save a JSON project file, or print an acceptance test sheet. The checklist is built in your browser, and projects and client templates can be saved to your account.

Does the tool perform the tests?

No. It is a commissioning documentation tool, not a measurement instrument. You take the readings with your own test equipment, and the tool records them and produces the acceptance documents.